Powering Southern Alberta with Wind

Region icon

ALBERTA

How multiple medium-voltage and fiber-optic cables were installed to carry power and data across a 48-turbine wind energy development.

Project

Wind Farm

Time Span

2022

Service Components

Medium-Voltage Cable Installation

Fiber-Optic Cable Installation

Goals

ROHL was brought in to complete the wind farm’s multi-cable installation over a short period of on-site work. The goal was to coordinate the installation across the site while keeping pace with the broader construction schedule.

The Landscape

The Landscape

Location:

Dunmore, AB

Terrain:

Sand and Gravel

Access:

Rural

Challenges

Installing nearly 24 km of power cable, fiber-optic cable, and grounding conductor in a single pass required accuracy. Each run had precise stopping points from splice and junction boxes, and turbine centre pins, leaving little room for measurement or placement errors.

Heavy cable reels added complexity, while existing infrastructure and wet ground conditions affected how crews could work across the site. With multiple trades operating at the same time, access and sequencing also had to be carefully coordinated to maintain progress.

  1. 01

    Precise Cable Placement

  2. 02

    Heavy Material Handling

  3. 03

    Wet Site Conditions

  4. 04

    Multi-Trade Coordination

Solutions section image

Solutions

ROHL used cable plowing rather than conventional open-trench methods to install the cables and conductor in a single pass. This approach reduces installation time, cost, and ground disturbance.

Where we were unable to direct plow, crews completed 15 horizontal directional drilling bore pulls to navigate crossings without disturbance. Pulling cable directly from the reels through each minimized the need for splicing. Every run was planned against engineered drawings and utility locates, while daily meetings with other trades kept schedules and work coordinated.

  1. 01

    Single-Pass Cable Plowing

  2. 02

    15 HDD Bore Pulls

  3. 03

    Minimal Splicing

  4. 04

    Coordinated Installation

THE IMPACT

Our cable-plowing approach made it possible to complete the installation between August and October, a schedule that conventional trenching could not have achieved.

Installing multiple cables in a single pass reduced installation time and cost while limiting disturbance to the surrounding land.

48

WIND TURBINES

24

KM MV cable plowed

TIMELINE

From Quote to Completion

01

Quote

July 2022

Project quote submitted

July 2022

02

Contract

August 2022

The project contract is confirmed

August 2022

03

Execution

Aug-Oct, 2022

Crews mobilized and carried out the cable installation

Aug-Oct, 2022

04

Complete

Oct 2022

Installation scope was completed

Oct 2022