Lyle Katerenchuk, Director, Design & Environmental Management
Designing on Real Numbers: What Honest Project Estimating Looks Like
Every infrastructure project begins with a number. A budget is approved, a bid is submitted, a schedule is promised. Those numbers set expectations, and they are very hard to walk back once they have been shared. When they are wrong, the consequences tend to show up later as change orders, disputes, strained relationships, and projects that deliver less than they promised.
At ROHL, the first step in how we work is to design on real numbers. It sounds simple, and it is one of the most difficult disciplines in construction. This article explains what we mean, why it matters, and what clients can expect to see when estimating is done honestly.
Why Estimates Go Wrong
Few estimates fail because someone did the arithmetic incorrectly. They fail because of the assumptions underneath the arithmetic.
• Unverified quantities. Lengths, crossings, and counts taken from a map or a prior project rarely match the field. Small differences multiply across a long route.
• Optimistic productivity. It is easy to price a project at the best rate a crew has ever achieved. It is harder, and more useful, to price at the rate that conditions will realistically allow.
• Ignored seasons. A schedule that looks fine on a calendar may place the hardest work in the worst conditions. Weather and ground conditions are part of the scope, even though they never appear on a drawing.
• Vague scope. When the scope of work leaves room for interpretation, each party tends to interpret it in its own favour. The gap becomes a dispute.
• Borrowed documents. Reusing a previous package without checking each line can carry over assumptions that no longer apply.
None of these problems is exceptional. Every experienced team has seen all of them. The difference is whether the estimating process is designed to catch them early.
Start With the Scope
A reliable number starts with a clear description of what is being built. That means precise scope boundaries: what is included, what is excluded, who supplies what, and what conditions the price depends on.
Clarity at this stage protects everyone. A well-written scope describes deliverables in terms that can be verified. It states assumptions explicitly, such as expected ground conditions, access, and approvals, so that if reality differs, the effect on cost and schedule can be discussed against a shared baseline rather than argued after the fact.
Experienced teams treat scope review as active work, not a formality. They read the documents looking for gaps, ambiguities, and unstated assumptions, and they raise them before pricing rather than after award. Asking those questions early can feel slow, but it is far cheaper than discovering the disagreement mid-project.
Verify What You Can
The most reliable quantities come from the field. Site visits, route walks, and review of existing records turn assumptions into information. They reveal crossings that were not on the plan, access limitations, ground conditions, and constraints that affect method and sequence.
Verification has a cost, and it is worth paying. A modest investment in understanding the site before pricing prevents much larger surprises during construction. Where verification is not possible, because of timing or access, the right response is to say so and state the assumption clearly, not to quietly guess.
Price the Productivity You Will Actually Get
Productivity is where estimates are most likely to drift from reality. Production rates vary by crew, equipment, soil, weather, and season. A rate that was achievable on one project in one set of conditions may be unrealistic in another.
Honest estimating draws on actual experience: what crews have achieved in comparable conditions, adjusted for what is known about the current site. It accounts for the time lost to mobilization, weather, inspections, and the interruptions that occur on every real project. It does not assume a perfect week.
This is where experience pays off. A team that has completed many projects across different conditions has a grounded sense of what is achievable, and where optimism tends to creep in. That track record is worth more than a polished spreadsheet.
Put the Calendar in the Numbers
Season is a design input, not a scheduling afterthought. The same work can cost more and take longer in frozen ground, saturated spring conditions, or a short construction window with heavy demand for crews and equipment.
A realistic estimate considers when each activity will happen, not just how long it will take. It checks that critical permits and materials are in place ahead of the construction window, and that the sequence avoids placing the most weather-sensitive work at the worst time of year. If a project must straddle seasons, that fact belongs in both the plan and the price.
Be Open About Risk
Every project carries uncertainty. Pretending otherwise does not make the risk disappear. It just moves it to a moment when it is harder to manage.
Good estimating identifies the principal risks, such as ground conditions, permit timing, weather, access, and supply availability, and deals with them openly. Some risks can be reduced through investigation or planning. Some can be allocated to the party best placed to manage them. Some simply need to be understood and monitored. In every case, a risk that has been named is a risk that can be discussed.
For clients, this openness is a sign of a mature partner. A bid that acknowledges what is uncertain, and explains how it will be handled, is more trustworthy than one that assumes everything will go perfectly.
Manage Change Without Drama
Even the best estimate meets surprises. Ground conditions differ, a stakeholder changes a requirement, a permit arrives late. What matters is how the team responds.
Change is manageable when the baseline is clear. If scope and assumptions were stated precisely, a difference can be identified, quantified, and discussed quickly. Early notice, clear documentation, and honest conversation keep adjustments from escalating into disputes.
The goal is not to avoid change, which is unrealistic, but to make it visible and fair. Clients should never learn about a cost or schedule impact from an invoice. They should hear about it as soon as it is understood, with the facts and the options laid out.
Keep the Numbers Honest as the Project Moves
Estimating is not a one-time event. A reliable number needs to stay connected to reality as work progresses. Regular reporting against the plan, covering progress, productivity, and emerging risks, keeps everyone informed and gives the team a chance to act while options remain open.
Teams that track actual performance against their assumptions also learn faster. They see where estimates held up and where they did not, and that knowledge feeds into the next project. Over time, honest feedback is what makes estimates better.
How Real Numbers Connect to the Rest of the Process
Designing on real numbers is the first of three steps in how ROHL approaches projects. The second is to permit and plan for the real season, and the third is to build and deliver what we committed. The steps depend on each other. A realistic design makes realistic planning possible, and realistic planning makes delivery achievable.
This is also why ROHL offers support across the full project cycle, from conception and planning through execution and lighting the fiber. When the team that develops the numbers is the team that delivers the work, there is no gap between the promise and the build. The assumptions made at the start are owned by the people who have to live with them, and that accountability tends to produce better estimates in the first place.
What to Look For in a Partner
If you are evaluating contractors or planning your own project estimates, a few signals indicate honest estimating.
1.They ask hard questions about scope before pricing. Good partners probe for gaps instead of quietly filling them with optimistic assumptions.
2.They have verified the site, or they say clearly that they have not. Stated assumptions are better than hidden ones.
3.They can explain their productivity assumptions. They should be able to show where the numbers come from.
4.They account for season and schedule. The plan should reflect the actual calendar, not a generic one.
5.They name the risks. Openness about uncertainty is a strength.
6.They have a clear approach to change. You should know in advance how differences will be handled.
Good numbers do not guarantee a good project, but bad numbers almost guarantee a difficult one. The investment in getting them right at the start is one of the best decisions an owner can make, and one of the clearest marks of a team worth working with.